3 distinct question groups available in the collected papers. More exam sessions are being collected.

A firm manufactures two types of products A and B and sells them at a profit of Rs.2 on type A and Rs.3 on type B. Each product is processes on the machines G aad H. Type A requires one minutc of processing time on G and two minutes on H, type B requires onc minute on G and one minute on H. the machine G is available for not more than 6 hours 40 minutes while machic H is available for 10 hours during any working day. Formulate the given problem as lincar programming problem.

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 1

Define Operation Rescarch. Explain the phases of Opcration Rescarch.

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 1

Solve the LPP by the simplex method, Maximize. 3xj + 2x1 Subject to, x| +x, ≤4 X,-X2≤2 X→X,≥0

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 1

Module 2

2 distinct question groups available in the collected papers. More exam sessions are being collected.

Obtain the initial basic feasible solution by, Vogel's approximation method. North-West comer rule method. Warehouse → W3 W's Available Factories + 1 2 6 4 Required Differentiate between Assignment problem and Transportation problem. A company has one surplus truck in each of the cities A, B, C, D and E and one deficit truck in cach of the cities 1, 2, 3. 4, 5 and 6. The distance between the cities in kilomcters is shown in the aatrix below. Find the assignment of trucks from cities in surplus to citics in deficit so that the total distance covered by vehiele is minimum. 5 12 10 | 15 | 10 18 25 15 16 • 11 | 6 14 | 12 |11|7 Four new machines Mi, Ma. My and Ma are to be installed in a machine shop. Therc an five vacant places A, B, C, D and E available. Because of limited space, Machine M: cannot be placed at C and M, cannot be placed at A, Cij, the assignment cost of machine i to place j in rupees is shown below. E D Mı M2 6 M÷

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1Original question scan, part 2
1 exam session
  • Dec-2025-Jan-2026 · PDF page 1

Q-3 Obtain the mathematical formulation of transportation problem.

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 1

Module 3

4 distinct question groups available in the collected papers. More exam sessions are being collected.

An organization has large number of activities but it is interested in controlling a part of these activities to 7 in number. The following data is available for thesc activities. Activity Precedence Time (days) La |4 10 15 D 10 F G D,E,F 10 | () Draw a PERT network for the activities (ї) Identify the critical path and its duration. (11) If the organization puts 47 days as dead line to complete, what is the probability of completion in 47 days.

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 2

Consider the network shown in Fig. Q6 (a). The thrce time estimates are given along the arrows. Determine the critical path. What is the probability that the project will be completed in 20 days? 0.5-1-7 12-2-8. (2) 4-6-8 1-15-11 Fig. Q6 (a)

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 3

Explain the basic steps involved in PERT/CPM. Explain the Fulkerson's rule for numbering the events.

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 2
Show 1 Backup Question

For the network shown below, find the critical path and validate. Fig. Q6 (b)

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 3

Module 4

3 distinct question groups available in the collected papers. More exam sessions are being collected.

minutes. The receptionist on duty lates an average of one minute per person. (Arrivals are as per exponentta) and services are as per Poisson distribution). (ї) What is the probability that 9 person will straight away meet the receptionist? For what portion of the time the receptionist is busy? What is the average length of queuc? What is the average number of patrons in the system? (1V) (У) What is the average waiting time of a person? (VI) What is the average time a patron spends in the system?

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 4

Module - Use the dominance rule and solve the following game whosc payoff matrix tor Player A is, -3 -3 _2

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 3

Solve the game by graphical method, B¿ B3 B+ Bş Аı -1 Az -4 -1|6-5 Define the term queuc. State and explain the characteristics of queuing system. Patrons arrive at 9 reception counter at an average inter arrival time of

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1Original question scan, part 2
1 exam session
  • Dec-2025-Jan-2026 · PDF page 3

Module 5

3 distinct question groups available in the collected papers. More exam sessions are being collected.

2. undergo through 2 machines Mi and M2 in the order M)M2. Job J1 J2 Machine M; 51 9 |3 |10 M≥ |2|6|7|84 Obtain the sequence for the jobs that minimizes the total elapsed time and also find the idle time of both the machines. There are five jobs, cach of which must go through the two machines A and B in the order AB processing time are given below : Job 12|34|5 Machine A 5 1 9|3|10 Machine B 267814 Determine a sequence for the five jobs that will minimize the total elapsed time. Six jobs A, B, C, D, E. and F have arrived at one time to be processed on single aachine. Determne Optimal sequence as per SPT rule. Completion time of the jobs. Mean flow tie. (IV) Avcrage in process inventory. Job BCD Processing time | Z|6 |8|4 Use graphical method. determine the optimal sequence needed to process

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 4

Consider the processing time (in minutes) of 5 jobs cach of which must

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 4

jobs 1 and 2 on five machincs A, B. C. D and F. For each machine find the job which should be done first. Also calculate the total time needed to complete both the jobs. Jobl Sequence A Tue E Job2 Seguence Tie 4

OCR transcription · Wording, symbols, or figures may be incomplete.

View question scan & diagramsOriginal question scan, part 1
1 exam session
  • Dec-2025-Jan-2026 · PDF page 4